2026 San Juan County Levy Audit Follow-up

Status of Work Completed

June 2026

Requirements

Requirement Topic Work completed on requirement Completed/pending completion Future follow-up?
1 Certification of assessed value to taxing districts The San Juan County Assessor (Assessor) implemented all required actions regarding the levy request certification in the 2026 tax year. Completed No

Note: Refer to our original report issued in July 2025 for a complete explanation of each requirement.

Recommendations

Recommendation Topic Work completed on recommendation Completed/pending completion Future follow-up?
1 County legislative authority certification to Assessor The Assessor  implemented all recommended actions regarding the levy request certification in the 2026 tax year. Completed No