NOTE: Refer to our original report issued in May 2016 for a complete explanation of each requirement.
| Requirement | Topic | Work Completed on Requirement | Completed / Pending Completion | Future Follow-up? |
|---|---|---|---|---|
| 1 | Board Orders | The Department remains concerned about the amount of time it takes for the orders to be shipped following the hearing and the number of orders being issued. The Board has made progress in reducing the time between hearings and shipping orders. 2016 Quarterly Breakdown:
The Department is concerned about the number of petitions where a hearing has been held and no order has been shipped as of August 10, 2016. Outstanding Orders Backlog:
The Board reported no hearings were held in July 2016. |
Pending | To determine if the Board of Equalization has met the requirement, the Department expects the Board of Equalization to provide:
|
| Recommendation | Topic | Work Completed on Recommendation | Completed / Pending Completion | Future Follow-up? |
|---|---|---|---|---|
| 1 | Streamline Process | The Board feels their process is efficient and does not plan on making any changes. | Completed | No |
| 2 | Roles of Board Members | The Board does not agree with this recommendation and does not plan on making any changes. | Completed | No |
| 3 | Sharing Board’s Decision the Day after Hearing | The Board provided audio recording for petition 15-0038. This recording did not contain the statement to call Clerk for the decision. | Completed | No |